How are steel coils produced at Tonggang?

Nov 17, 2026 Leave a message

Ryan Kim
Ryan Kim
Specializing in CNC machining services, Ryan ensures that all components are precision-machined to meet the highest standards. His expertise is crucial for maintaining the quality of our products.

 

The production of hot-rolled steel coils at Tonggang involves several main stages, including steelmaking, continuous casting, slab reheating, rough rolling, finish rolling, laminar cooling and coiling. After steelmaking and secondary refining, molten steel is continuously cast into slabs. These slabs are then processed through the hot rolling line to produce strip with the required thickness and width before cooling and coiling.

Depending on product specifications and downstream requirements, hot-rolled coils may undergo further processing such as leveling, slitting, cut-to-length shearing, pickling, galvanizing or coating. The specific operations vary according to the intended product.

Steelmaking and slab preparation

Continuous casting slabs are the main feedstock for hot-rolled steel coil production. After converter steelmaking and secondary refining, molten steel enters the continuous casting machine and solidifies into slabs suitable for rolling.

According to publicly available information, Tonggang operates billet continuous casting machines and thin slab continuous casting machines, as well as a 1560 mm hot-rolled ultra-thin strip production line. The slab dimensions, transfer arrangements and rolling processes depend on the specific production line.

Before entering the hot rolling process, slabs are classified and scheduled according to production requirements. Depending on the casting and rolling line configuration, the connection between continuous casting and rolling may involve hot charging, temporary storage in a holding pit or direct transfer to the rolling process. These arrangements help reduce slab temperature loss and coordinate production between the two sections.

Slab reheating

Slabs that require reheating are transported by roller tables into a reheating furnace. They pass through preheating, heating and soaking zones to reach the temperature required for rolling.

The heating temperature depends on the steel grade, slab thickness and rolling schedule. A typical process reference is approximately 1200°C. The slabs also require sufficient soaking time to achieve a reasonably uniform temperature distribution across the section. Uneven heating can affect rolling loads and finished product quality.

Once the required temperature is reached, the discharge equipment transfers the slabs onto the roller table for descaling and rolling.

High-pressure water descaling and rough rolling

Oxide scale forms on the slab surface during reheating. Before rough rolling, a high-pressure water descaling system removes this scale to reduce the risk of surface defects caused by scale being pressed into the steel.

The roughing stage reduces slab thickness substantially and produces an intermediate transfer bar for finish rolling.

Depending on the mill configuration, the roughing section may include a sizing press, vertical rolls and two-high or four-high roughing stands. The sizing press adjusts slab width, while vertical rolls control strip width. Horizontal rolling stands reduce thickness through successive rolling passes.

For production lines with the corresponding roughing configuration, the intermediate slab may have a thickness of 30 to 60 mm. After roughing, the transfer bar travels along the roller table and enters a holding or finishing section according to the mill layout.

Crop shearing and finish rolling

Before entering the finishing train, the transfer bar generally passes through crop shears to remove irregular head and tail sections. It then undergoes another high-pressure water descaling operation to remove oxide scale formed during the preceding stages.

Finish rolling is carried out by a continuous multi-stand finishing train. For example, a line equipped with seven stands designated F1 to F7 reduces the intermediate slab to the required finished strip thickness through successive rolling passes.

The original process reference gives a finished strip thickness range of 1.2 to 25.4 mm. The actual production range depends on the steel grade, mill capacity and product specifications.

During finish rolling, the computer control system adjusts roll reductions, roll gaps and other rolling parameters according to measured data and calculated process models. These adjustments control strip thickness, profile and flatness.

The strip remains at a relatively high temperature when it leaves the finishing train. The original process reference gives an approximate finishing temperature of 850°C. The actual value depends on the steel grade and the required final microstructure and mechanical properties.

Laminar cooling

After leaving the finishing train, the strip travels along the run-out table and enters the laminar cooling section. The cooling system adjusts water flow and cooling conditions according to the steel grade, strip thickness, width and target coiling temperature.

The original process reference specifies a coiling temperature range of 550 to 650°C. The cooling schedule affects phase transformation, mechanical properties and finished product quality, so it must be selected according to the individual steel grade.

During cooling, the production line must maintain uniform temperature distribution across the upper and lower strip surfaces and ensure stable strip movement. Uneven cooling can affect strip flatness and subsequent coiling quality.

Coiling, coil unloading and storage

After reaching the target coiling temperature, the strip travels along the run-out table to the coiler. The pinch rolls, wrapper rolls and coiler mandrel work together to guide the strip head and wind the strip into a coil with the required outside diameter and weight.

During coiling, strip speed, mandrel speed and winding tension must remain coordinated. This helps maintain tight winding and aligned coil edges while reducing loose coils, telescoping and other coil shape defects.

After coiling, the mandrel contracts to release the coil. An unloading car supports the coil and transfers it to the storage area. Depending on production requirements, the coil undergoes inspection, weighing, marking and strapping before entering the finished goods warehouse or moving to a downstream processing facility.

Downstream processing of hot-rolled steel coils

After hot rolling and coiling, steel coils may enter different finishing or further processing lines according to their intended applications. These operations are optional downstream processes. A coil does not necessarily pass through all of them.

Leveling and slitting

Some hot-rolled coils undergo leveling to improve strip flatness and surface condition. Products requiring further straightening may also pass through a leveler or other roll straightening equipment.

After the required treatment, slitting equipment divides the coil into narrower coils with specified widths or weights. The original process description includes a six-roll straightener and a leveling or skin-pass mill. Their functions and arrangement depend on the specific processing line.

Cut-to-length processing

For products required in sheet form, the steel coil is first unwound and then processed through leveling, edge trimming and flying shearing equipment.

The flying shear cuts the strip to a preset length. A stacking system then collects and stacks the finished sheets.

The original process reference specifies a flying shear length accuracy of ±1 mm. This value must be verified against the actual equipment capability and cutting requirements of the production line.

Surface treatment

Depending on product requirements, hot-rolled coils may undergo pickling, galvanizing or coating.

Pickling removes oxide scale from the hot-rolled strip surface. Products requiring greater corrosion resistance or a specified surface finish may undergo further galvanizing or coating processes according to the material and production route.

These operations require dedicated processing equipment and are not part of the hot rolling and coiling stages themselves. Some products may also undergo cold rolling before subsequent surface treatment.

Cutting

When specific dimensions are required, steel products can be processed to length using shearing or sawing. The choice of cutting method depends on steel thickness, shape, dimensions and subsequent application requirements.

Main process parameters for hot-rolled steel coil production

The following table summarizes the parameter examples provided in the original process description. Actual production settings must be confirmed against the steel grade, product dimensions and rolling mill process specifications.

Process item Parameter reference
Slab reheating temperature Approximately 1200°C
Intermediate slab thickness after roughing 30 to 60 mm
Finished strip thickness after finishing 1.2 to 25.4 mm
Finishing temperature Approximately 850°C
Coiling temperature 550 to 650°C
Coiling temperature control deviation ±15°C
Flying shear length accuracy ±1 mm

Custom machining of components for steel processing equipment

Hot rolling production lines contain work rolls, roller shafts, coiler shaft assemblies, drive connections and other mechanical components. Their dimensional accuracy and structural design affect equipment installation and operation.

When standard components cannot meet specific installation or structural requirements, we can manufacture non-standard precision parts according to customer drawings. Both single-piece and small-batch machining are supported.

Hansheng Automation also provides custom machining for components used in other industries, including tobacco and packaging machinery, filling equipment, yacht equipment and RC racing cars. Parts are manufactured according to customer drawings and individual machining requirements.

Mining--Metallurgical-Machinery